Standards & Requirements for LevelingVertical Control Network StandardsWhen a vertical control point is classified with a particular order and class, NGS certifies that the orthometric elevation at that point bears a relation of specific accuracy to the elevations of all other points in the vertical control network. That relation is expressed as an elevation difference accuracy, b. An elevation difference accuracy is the relative elevation error between a pair of control points that is scaled by the square root of their horizontal separation traced along existing level routes.
An elevation difference accuracy, b, is computed from a minimally constrained, correctly weighted, least squares adjustment by b = S/vd where d = approximate horizontal distance in kilometers between control point
positions traced along existing level routes. The elevation difference accuracy pertains to all pairs of points (but in practice is computed for a sample). The worst elevation difference accuracy (largest value) is taken as the provisional accuracy. If this is substantially larger or smaller than the intended accuracy, then the provisional accuracy takes precedence. As a test for systematic errors, the variance factor ratio of the new survey is computed by the Iterated Almost Unbiased Estimator (IAUE) method described in appendix B. This computation combines the new survey measurements with existing network data, which are assumed to be correctly weighted and free of systematic error. If the variance factor ratio is substantially greater than unity, then the survey does not check with the network, and both the survey and the network data will be examined by NGS. Computer simulations performed by NGS have shown that a variance factor ratio greater than 1.5 typically indicates systematic errors between the survey and the network. Setting a cutoff value higher than this could allow undetected systematic error to propagate into the national network. On the other hand, a higher cutoff value might be considered if the survey has only a small number of connections to the network, because this circumstance would tend to increase the variance factor ratio. In some situations, a survey has been designed in which different sections
provide different orders of control. For these multi-order surveys, the
computed elevation difference accuracies should be grouped into sets appropriate
to the different parts of the survey. Then, the largest value of b in
each set is used to classify the control points of that portion, as discussed
above. If there are sufficient connections to the network, several variance
factor ratios, one for each section of the survey, should be computed. Vertical ExampleSuppose a survey with an intended accuracy of second-order, class II has been performed. A series of propagated elevation difference accuracies from a minimally constrained adjustment is now computed.
Suppose that the worst elevation difference accuracy is 1.32. This is not substantially different from the intended accuracy of 1.3 which would therefore have precedence for classification. It is not feasible to precisely quantify "substantially different." Judgment and experience are determining factors. Now assume that a solution combining survey and network data has been obtained (as per appendix B), and that a variance factor ratio of 1.2 was computed for the survey. This would be reasonably close to unity and would indicate that the survey checks with the network. The survey would then be classified as second-order, class II, using the intended accuracy of 1.3. However, if a survey variance factor ratio of, say, 1.9 was computed, the survey would not check with the network. Both the survey and network measurements then would have to be scrutinized to find the problem. MonumentationControl points should be part of the National Geodetic Vertical Network only if they possess permanence, vertical stability with respect to the Earth's crust, and a vertical location that can be defined as a point. A 30-centimeter- long wooden stake driven into the ground, for example, would lack both permanence and vertical stability. A rooftop lacks stability and is difficult to define as a point. Typically, corrosion resistant metal disks set in large rock outcrops or long metal rods driven deep into the ground have the necessary qualities. Replacement of a temporary mark by a more permanent mark is not acceptable unless the two marks are connected in timely fashion by survey observations of sufficient accuracy. Detailed information may be found in NOAA Manual NOS NGS 1,"Geodetic bench marks." Geodetic Leveling RequirementsGeodetic leveling is a measurement system comprised of elevation differences observed between nearby rods. Leveling is used to extend vertical control. Network Geometry
New surveys are required to tie to existing network bench marks at the beginning and end of the leveling line. These network bench marks must have an order (and class) equivalent to or better than the intended order (and class) of the new survey. First-order surveys are required to perform check connections to a minimum of six bench marks, three at each end. All other surveys require a minimum of four check connections, two at each end. "Check connection" means that the observed elevation difference agrees with the adjusted elevation difference within the tolerance limit of the new survey. Checking the elevation difference between two bench marks located on the same structure, or so close together that both may have been affected by the same localized disturbance, is not considered a proper check. In addition, the survey is required to connect to any network control points within 3 km of its path. However, if the survey is run parallel to existing control, then the following table specifies the maximum spacing of extra connections between the survey and the control. At least one extra connection should always be made.
top Instrumentation
Only a compensator or tilting leveling instrument with an optical micrometer
should be used for first-order leveling. Leveling rods should be one piece.
Wooden or metal rods may be employed only for third-order work. A turning
point consisting of a steel turning pin with a driving cap should be utilized.
If a steel pin cannot be driven, then a turning plate ("turtle") weighing
at least 7 kg should be substituted. In situations allowing neither turning
pins nor turning plates (sandy or marshy soils), a long wooden stake with
a double-headed nail should be driven to a firm depth. Calibration Procedures
Compensator-type instruments should be checked for proper operation at
least every 2 weeks of use. Rod calibration should be repeated whenever
the rod is dropped or damaged in any way. Rod levels should be checked
for proper alignment once a week. The manufacturer's calibration standard
should, as a minimum, describe scale behavior with respect to temperature. Field Procedures
Double-run leveling may always be used, but single-run leveling done with the double simultaneous procedure may be used only where it can be evaluated by loop closures. Rods should be leap-frogged between setups (alternate setup method). The date, beginning and ending times, cloud coverage, air temperature (to the nearest degree), temperature scale, and average wind speed should be recorded for each section plus any changes in the date, instrumentation, observer or time zone. The instrument need not be off-leveled/releveled between observing the high and low scales when using an instrument with a reversible compensator. The low-high scale difference tolerance for a reversible compensator is used only for the control of blunders. With double scale rods, the following observing sequence should be used:
Office Procedures
The normalized residuals from a minimally constrained least squares adjustment will be checked for blunders. The observation weights will be checked by inspecting the postadjustment estimate of the variance of unit weight. Elevation difference standard errors computed by error propagation in a correctly weighted least squares adjustment will indicate the provisional accuracy classification. A survey variance factor ratio will be computed to check for systematic error. The least squares adjustment will use models that account for:
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||